Particulars | NOV-2000 | MAR-2020 |
As on
31-08-2023
| % Increase |
No. of 33/ 11 KV Substations | 248 | 1314 |
1361
|
448%
|
Length of 33 KV Line (in KM) | 6988 | 22898 |
24569
|
252%
|
No. of 11/ 0.4 KV Sub Station | 29692 | 180691 |
220520
|
643%
|
Length of 11 KV Line (in KM) | 40556 | 116872 |
130608
|
222%
|
Length of LT Line (in KM) | 51314 | 199109 |
225645
|
340%
|
No. of Electrified Villages | 17108 | 19567 |
19588
|
14.37%
|
Electrification Percentage | 87.43 | 100.00 |
100
|
14.37%
|
No. of Electrified Majra Tola | 10375 | 39344 |
40375
|
289%
|
No. of Energised Pumps | 73369 | 443424 |
531936
|
625%
|
No. of BPL Connections | 630389 | 1960318 |
1616400
|
156%
|