Achievement Milestones
|
Strengthening of T&D Network till |
Aug - 2023
|
|
1 (a)
|
New Constructions
|
|
(i)
|
33 KV Lines
|
17581
Kms |
|
(ii)
|
11 KV Lines
|
90052
Kms |
|
(iii)
|
LT Lines
|
174331
Kms. |
|
(iv)
|
33/11 KV Sub Stations
|
1113
Nos. |
|
(v)
|
11/ 0.40 KV Sub Station
|
190828
Nos. |
|
1 (b)
|
Additional
|
|
(i)
|
33/11 KV Power Transformers at Various locations
|
739
Nos.
|
|
1 (c )
|
Augmentation |
|
(i)
|
33/11 KV Power Transformers at Various locations
|
1035
Nos.
|
|
(ii)
|
11/0.4 KV Distribution Transformers at various locations
|
16448
Nos. |
|